Guide to JCT design and build contract 2016 /
Guide to JCT Design and Build Contract 2016, the new edition ofthe author'sever popular Guide to DB11, is a practical guide to the operation and administration of the JCT Design & Build Building Contract suite 2016. All of the contract's provisions, procedures and conditions are organi...
Clasificación: | Libro Electrónico |
---|---|
Autor principal: | |
Formato: | Electrónico eBook |
Idioma: | Inglés |
Publicado: |
Newcastle upon Tyne :
RIBA Publishing,
[2017]
|
Temas: | |
Acceso en línea: | Texto completo (Requiere registro previo con correo institucional) |
Tabla de Contenidos:
- Machine generated contents note: 1.Introduction to design and build procurement
- The architect's role
- Novation
- Consultant switch
- Some general principles of design liability
- 2.About DB16
- Key features
- Deciding on DB16
- Comparison with SBC16
- Changes in the 2016 edition
- 3.Documents
- Employer's requirements
- Contractor's proposals
- Contract sum analysis
- BIM and other protocols
- Health and safety documents
- Bonds
- Sub-contract documents
- Domestic sub-contracts
- Use of documents
- Interpretation, definitions
- Priority of contract documents
- Discrepancies and errors
- Employer's requirements and contractor's proposals
- Divergences from statutory requirements
- Custody and control of documents
- Performance bonds and guarantees
- Assignment and third party rights
- Assignment
- Third party rights/warranties
- Procedure with respect to third party rights and warranties
- 4.Obligations of the contractor
- Note continued: The design obligation
- Standards and quality
- Obligations in respect of quality of sub-contracted work
- Compliance with statute
- Health and safety legislation
- 5.Possession and completion
- Possession by the contractor
- Progress
- Completion
- Pre-agreed adjustment
- Extensions of time
- Principle
- Procedure
- Assessment
- Partial possession
- Use or occupation before practical completion
- Practical completion
- Procedure at practical completion
- Failure to complete by the completion date
- Liquidated and ascertained damages
- 6.Control of the works
- Employer's agent
- Site manager and contractor's persons
- Principal contractor
- Principal designer
- Employer's obligations
- Information to be provided by the contractor
- Design submission procedure
- Schedule 1 procedure
- Employer's instructions
- Changes
- Goods, materials and workmanship
- Defective work
- Sub-contracted work
- Named sub-contractors
- Note continued: Work not forming part of the contract/persons engaged by the employer
- Making good defects
- 7.Sums properly due
- Valuation of changes in the employer's requirements and provisional sum work
- Supplemental Provision 2: contractor's estimates
- Cost saving and value improvement
- Valuation under the valuation rules
- Measurable work
- contract sum analysis
- Daywork
- fair valuation
- Reimbursement of direct loss and/or expense
- Alternative procedure using Supplemental Provision 2 estimate
- Alternative procedure using Supplemental Provision 3 estimate
- Matters for which loss and expense can be claimed
- Fluctuations
- 8.Payment
- Timing of payments
- Ascertainment of amounts due
- Value of work
- Unfixed materials
- `Listed items'
- Costs and expenses due to suspension
- Other items in the gross valuation
- Deductions from the gross valuation
- Withheld percentage
- Advance payments and bond
- Payment procedure
- Note continued: Deductions
- Employer's obligation to pay
- Contractor's position if the amount applied for is not paid
- Interim payment after practical completion
- Final payment
- Conclusive effect of final statement
- 9.Indemnity and insurance
- Injury to persons and damage to property caused by the negligence of the contractor
- Damage to property not caused by the negligence of the contractor
- Insurance of the works
- Action following damage to the works
- Terrorism cover
- Professional indemnity insurance
- Joint Fire Code
- Other insurance
- 10.Default and termination
- Repudiation or termination
- Termination by the employer
- Insolvency of the contractor
- Consequences of termination by the employer
- Termination by the contractor
- Consequences of termination by the contractor
- Termination by either the employer or the contractor
- Termination of named sub-contractor's employment
- 11.Dispute resolution
- Note continued: Notification and negotiation
- Mediation
- Adjudication
- Arbitration
- Arbitration and adjudication
- Arbitration or litigation
- References
- Publications
- Cases
- Legislation.