Collaborative risk mitigation through construction planning and scheduling : risk doesn't have to be a four letter word /
In the complex, cash-strapped, high pressure world of modern construction, what do you do when something goes wrong? This work looks beyond the best-case scenario to give project managers, contractors, architects and engineers the tools to prepare effectively for the unexpected.
Clasificación: | Libro Electrónico |
---|---|
Autor principal: | |
Formato: | Electrónico eBook |
Idioma: | Inglés |
Publicado: |
Bingley, UK :
Emerald Publishing Limited,
2019.
|
Edición: | First edtion. |
Temas: | |
Acceso en línea: | Texto completo |
Tabla de Contenidos:
- Synopsis from Industry Professionals
- About the Author
- Purpose of This Book
- Acknowledgments
- Introduction
- Chapter 1 Has It Ever Gone As Planned?
- 1.1. Change Is the Only Constant
- 1.2. Forms of Risk
- Chapter 2 Who Benefits from Planning and How?
- 2.1. Planning
- 2.2. Scheduling
- 2.3. Risk Identification.
- 2.4. Benefits
- Chapter 3 Real Construction Mitigation Case Studies
- Case Study #1: Leadership Consistency, Scope Re-Design During Construction, Inflation, And Hurricanes, "Oh, My!"
- 3.1. Project Scope
- 3.2. Key Project Milestone Dates
- 3.3. Practitioner Team Members
- 3.4. Situation and Risks
- 3.5. Mitigation Efforts
- 3.5.1. Leadership Consistency
- 3.5.2. Scope Changes & Schedule Mitigation
- 3.5.3. Budget Control Risk Mitigation
- 3.6. Practices
- 3.6.1. Leadership Consistency Practices
- 3.6.2. Scope Change and Time Management Practices
- 3.6.3. Budget Control Practices.
- 3.6.4. Environmental Risk Practices
- 3.7. Final Outcome and Benefits
- 3.7.1. Tangibles
- 3.7.2. Intangibles
- 3.8. Summation
- Case Study #2: Team Integration, Decision-Making, and Schedule Reporting, are Critical Factors for Scheduling Success
- 3.9. Project Scope
- 3.10. Key Project Milestone Dates
- 3.11. Practitioner Team Members
- 3.12. Situation and Risks
- 3.13. Mitigation Efforts
- 3.13.1. Team Risk with Integration Mitigation
- 3.13.2. Decision-Making Risk Mitigation
- 3.13.3. Risk Mitigation through Schedule Reporting
- 3.13.4. Environmental Risk Mitigation
- 3.14. Practices.
- 3.14.1. Team Integration and Decision-Making
- 3.14.2. Information Management and Reporting
- 3.15. Final Outcome and Benefits
- 3.15.1. Tangibles
- 3.15.2. Intangibles
- 3.16. Summation
- Chapter 4 Risk Management Matrix
- 4.1. Part I: Risk Identification
- Owner/End User Perspective
- 4.2. Part II: Risk Identification
- Design and Construction Perspective
- 4.3. Part III: Risk Identification
- Schedule Elements
- Chapter 5 Communicating the Project Schedule and Change Management
- 5.1. Part I: Communicating through Shared Language
- 5.2. Part II: Achieving Mutual Agreement with the Baseline Schedule.
- 5.3. Part III: Periodic Schedule Reporting
- 5.4. Part IV: Perfecting Contractual Time Extension Requests
- 5.5. Part V: Internal Reporting of Schedule Performance
- 5.6. Part VI: Close-Out Executive Reporting
- Chapter 6 Contingency Planning
- 6.1. Part I: Understanding the Difference Between Contingency and Mitigation
- 6.2. Part II: Reporting a Contingency Plan
- Chapter 7 Implementing Mitigation Measures Through Technological Application of the Computer Scheduling Software
- 7.1. Part I: Technical Parameters of Activities which Reduce Risk.