Cargando…

Collaborative risk mitigation through construction planning and scheduling : risk doesn't have to be a four letter word /

In the complex, cash-strapped, high pressure world of modern construction, what do you do when something goes wrong? This work looks beyond the best-case scenario to give project managers, contractors, architects and engineers the tools to prepare effectively for the unexpected.

Detalles Bibliográficos
Clasificación:Libro Electrónico
Autor principal: Lana, Kay Coble (Autor)
Formato: Electrónico eBook
Idioma:Inglés
Publicado: Bingley, UK : Emerald Publishing Limited, 2019.
Edición:First edtion.
Temas:
Acceso en línea:Texto completo

MARC

LEADER 00000cam a2200000 i 4500
001 on1061275199
003 OCoLC
005 20231005004200.0
006 m o d
007 cr cnu|||unuuu
008 181106s2019 enka ob 001 0 eng d
040 |a N$T  |b eng  |e rda  |e pn  |c N$T  |d N$T  |d OCLCF  |d N$T  |d AU@  |d QGK  |d OCLCQ  |d OCLCO  |d OCLCQ  |d OCLCO 
020 |a 9781787431478  |q (electronic bk.) 
020 |a 1787431479  |q (electronic bk.) 
020 |z 9781787431485 
029 1 |a AU@  |b 000065427648 
035 |a (OCoLC)1061275199 
050 4 |a HD61 
072 7 |a BUS  |x 082000  |2 bisacsh 
072 7 |a BUS  |x 041000  |2 bisacsh 
072 7 |a BUS  |x 042000  |2 bisacsh 
072 7 |a BUS  |x 085000  |2 bisacsh 
082 0 4 |a 658.155  |2 23 
049 |a UAMI 
100 1 |a Lana, Kay Coble,  |e author. 
245 1 0 |a Collaborative risk mitigation through construction planning and scheduling :  |b risk doesn't have to be a four letter word /  |c by Lana Kay Coble. 
250 |a First edtion. 
264 1 |a Bingley, UK :  |b Emerald Publishing Limited,  |c 2019. 
300 |a 1 online resource 
336 |a text  |b txt  |2 rdacontent 
337 |a computer  |b c  |2 rdamedia 
338 |a online resource  |b cr  |2 rdacarrier 
504 |a Includes bibliographical references and index. 
588 0 |a Online resource; title from PDF title page (EBSCO, Nov. 7, 2018). 
505 0 |a Synopsis from Industry Professionals -- About the Author -- Purpose of This Book -- Acknowledgments -- Introduction -- Chapter 1 Has It Ever Gone As Planned? -- 1.1. Change Is the Only Constant -- 1.2. Forms of Risk -- Chapter 2 Who Benefits from Planning and How? -- 2.1. Planning -- 2.2. Scheduling -- 2.3. Risk Identification. 
505 8 |a 2.4. Benefits -- Chapter 3 Real Construction Mitigation Case Studies -- Case Study #1: Leadership Consistency, Scope Re-Design During Construction, Inflation, And Hurricanes, "Oh, My!" -- 3.1. Project Scope -- 3.2. Key Project Milestone Dates -- 3.3. Practitioner Team Members -- 3.4. Situation and Risks -- 3.5. Mitigation Efforts -- 3.5.1. Leadership Consistency -- 3.5.2. Scope Changes & Schedule Mitigation -- 3.5.3. Budget Control Risk Mitigation -- 3.6. Practices -- 3.6.1. Leadership Consistency Practices -- 3.6.2. Scope Change and Time Management Practices -- 3.6.3. Budget Control Practices. 
505 8 |a 3.6.4. Environmental Risk Practices -- 3.7. Final Outcome and Benefits -- 3.7.1. Tangibles -- 3.7.2. Intangibles -- 3.8. Summation -- Case Study #2: Team Integration, Decision-Making, and Schedule Reporting, are Critical Factors for Scheduling Success -- 3.9. Project Scope -- 3.10. Key Project Milestone Dates -- 3.11. Practitioner Team Members -- 3.12. Situation and Risks -- 3.13. Mitigation Efforts -- 3.13.1. Team Risk with Integration Mitigation -- 3.13.2. Decision-Making Risk Mitigation -- 3.13.3. Risk Mitigation through Schedule Reporting -- 3.13.4. Environmental Risk Mitigation -- 3.14. Practices. 
505 8 |a 3.14.1. Team Integration and Decision-Making -- 3.14.2. Information Management and Reporting -- 3.15. Final Outcome and Benefits -- 3.15.1. Tangibles -- 3.15.2. Intangibles -- 3.16. Summation -- Chapter 4 Risk Management Matrix -- 4.1. Part I: Risk Identification -- Owner/End User Perspective -- 4.2. Part II: Risk Identification -- Design and Construction Perspective -- 4.3. Part III: Risk Identification -- Schedule Elements -- Chapter 5 Communicating the Project Schedule and Change Management -- 5.1. Part I: Communicating through Shared Language -- 5.2. Part II: Achieving Mutual Agreement with the Baseline Schedule. 
505 8 |a 5.3. Part III: Periodic Schedule Reporting -- 5.4. Part IV: Perfecting Contractual Time Extension Requests -- 5.5. Part V: Internal Reporting of Schedule Performance -- 5.6. Part VI: Close-Out Executive Reporting -- Chapter 6 Contingency Planning -- 6.1. Part I: Understanding the Difference Between Contingency and Mitigation -- 6.2. Part II: Reporting a Contingency Plan -- Chapter 7 Implementing Mitigation Measures Through Technological Application of the Computer Scheduling Software -- 7.1. Part I: Technical Parameters of Activities which Reduce Risk. 
520 |a In the complex, cash-strapped, high pressure world of modern construction, what do you do when something goes wrong? This work looks beyond the best-case scenario to give project managers, contractors, architects and engineers the tools to prepare effectively for the unexpected. 
590 |a Emerald Insight  |b Emerald All Book Titles 
650 0 |a Construction industry  |x Risk management. 
650 0 |a Production scheduling. 
650 0 |a Strategic planning. 
650 6 |a Construction  |x Industrie  |x Gestion du risque. 
650 6 |a Ordonnancement (Gestion) 
650 6 |a Planification stratégique. 
650 7 |a BUSINESS & ECONOMICS  |x Industrial Management.  |2 bisacsh 
650 7 |a BUSINESS & ECONOMICS  |x Management.  |2 bisacsh 
650 7 |a BUSINESS & ECONOMICS  |x Management Science.  |2 bisacsh 
650 7 |a BUSINESS & ECONOMICS  |x Organizational Behavior.  |2 bisacsh 
650 7 |a Construction industry  |x Risk management  |2 fast 
650 7 |a Production scheduling  |2 fast 
650 7 |a Strategic planning  |2 fast 
856 4 0 |u https://emerald.uam.elogim.com/insight/publication/doi/10.1108/9781787431478  |z Texto completo 
938 |a EBSCOhost  |b EBSC  |n 1857503 
994 |a 92  |b IZTAP